| AMARAVATI WATER SUPPLY PROJECT |
| Site |
: |
Amaravati, Maharashtra |
| Client |
: |
Maharashtra Jeevan
Pradhikaran, Sholapur, Maharashtra |
| Contract Value |
: |
Rs. 1289.00 lakhs |
| Total Length |
: |
31.63 kms. of 1500 mm dia PSC Pipeline. |
|
|
| MANJIRA WATER SUPPLY SCHEME, PHASE - IV |
| Site |
: |
Singur Dam to Peddapur Village,
A.P. |
| Client |
: |
HMWS&SB, Hyderabad |
| Contract Value |
: |
Rs. 1880.00 lakhs |
| Total Length |
: |
20 kms. of 2000 mm. RCC Pipes. |
|
|
| COIMBATORE WATER SUPPLY PROJECT |
| Site |
: |
Coimbatore, Tamilnadu |
| Client |
: |
Tamilnadu Water
Supply & Sewerage Board |
| Contract Value |
: |
Rs. 709.00 lakhs |
| Total Length |
: |
14.00 kms. of 1500
mm, dia PSC Pipeline |
|
Awarded
maximum bonus payment for completing the job ahead of schedule.
|
|
|
| SHOLAPUR WATER
SUPPLY SCHEME |
| Site |
: |
Sholapur, Maharashtra |
| Client |
: |
Maharashtra Jeevan
Pradhikaran, Sholapur, Maharashtra |
| Contract Value |
: |
Rs. 1513.00 lakhs |
| Total Length |
: |
37.50 kms. of 1100
mm. dia PSC Pipeline |
|
Work aidded by OECF, Japan through HUDCO.
|
|
|
| AMARACHINTA LIFT
IRRIGATION SCHEME |
| Site |
: |
Amarachinta,
Atmakur Mahaboobnagar, A.P |
| Client |
: |
APSIDC |
| Contract Value |
: |
Rs. 427.00 lakhs |
| Scope |
: |
PSC / RCC Pipes -
5.1 kms. Pump House, Centrifugal Pumpsets, Squirrel Cage Induction
Motors, Transformer Yard, Copper-wound Transformers.
|
|
|
| DHARNASAR &
SARDARSHAHAR PIPELINE |
| Site |
: |
Dharnasar and
Sardarshahar, Rajasthan |
| Client |
: |
Public Health
Engineering Department, Churu, Rajasthan |
| Contract Value |
: |
Rs. 4555.00 lakhs |
| Total Length |
: |
93.30 kms. of 1100
mm dia PSC Pipes |
|
With
most modern equipment transportation fleets and quality work force,
BRC laid 93.30 kms. of pipeline in sandy in the most remote and
inaccessible locations of the Rajasthan desert.
|
|
|
| SINGAPUR TO
LINGAMPALLY MASTER BALANCING RESERVOIR |
| Site |
: |
Singapur to
Lingampally, A.P |
| Client |
: |
HMWS&SB,
Hyderabad |
| Contract Value |
: |
Rs. 521.72 lakhs |
| Total Length |
: |
5.34 kms. of 1200
mm dia PSC Pipeline |
|
The
work was completed five weeks before the stipulated date of
completion in a project duration of five months.
|
|
|
| WATER SUPPLY PROJECT
UNDER FLOURIDE CONTROL PROJECT |
| Site |
: |
Ajmer, Rajasthan |
| Client |
: |
Public Health
Engineering Department Circle, Ajmer |
| Contract Value |
: |
Rs. 778.00 lakhs |
| Total Length |
: |
13.44 kms. - 1100
mm PSC Pipeline |
| Completion Date |
: |
December - 2002. |
|
|
| CPWS SCHEME TO
NALLACHERUVU |
| Site |
: |
Anantapur, A.P |
| Client |
: |
(PR) RWS Circle, Anantapur, A.P |
| Contract Value |
: |
Rs. 636.00 lakhs |
| Total Length |
: |
Work includes
laying a PSC, DI, HDPE, PVC Pipeline for a length of 85.00 Kms. 55 structures like GLSRs, OHSRs, OHBRs, Pump House, Clear Water
Sumps
|
|
85 kms. of pipeline has been laid through remote and inaccessible
locations to provide drinking water to 55 habitations in Anantapur
district.
|
|
|
| CHURU - BISSAU WATER
SUPPLY PROJECT |
| Site |
: |
Churu, Rajasthan |
| Client |
: |
Churu - Bissau
Project Division, PHED, Rajasthan |
| Contract Value |
: |
Rs. 1840.00 lakhs |
| Total Length |
: |
31.70 kms. - 900
mm PSC Pipeline. |
|
|
| KRISHNA WATER SUPPLY
PROJECT |
| Site |
: |
Nagarjuna Sagar,
Hyderabad Road, A.P |
| Client |
: |
HMWS & SB,
Hyderabad |
| Contract Value |
: |
Rs. 3850.00 lakhs |
| Total Length |
: |
14.30 kms. of 2200
mm MS Pipeline |
|
It
was for a proven track record of reliability, professional
management and dedication of qualified professionals, that the
prestigious project for providing Krishna Waters to the metropolitan
areas of Hyderabad and Secunderabad was entrusted to BRC. These are
no ordinary pipelines, but the very lifeline for residents of
Hyderabad.
|
|
|
| WATER SUPPLY SCHEME
PHASE - IV |
| Site |
: |
Mohali, Punjab |
| Client |
: |
Public Health (GW)
Division, Mohali |
| Contract Value |
: |
Rs. 3094.00 lakhs |
| Total Length |
: |
25 kms - 1200 mm
PSC Pipes. |
|
|